Singapore HDB Remodelling Day 75



Day 75 of restoration
Singapore 5-room resale HDB restoration

Day 1 – 3 : Hack
Day 5 – 19 (2 weeks) : Tiling (Living space, bed rooms, cooking area, restroom)
Day 20 : Bathroom Doors, Bathroom Add-on Marking
Day 23 : 1st Paint Day (Ceiling, living space, bed spaces) + Gas Pipeline Installment, Dismantled Gas Meter
Day 26 : Paint (incorrect colour??), bed room doors & maindoor setups, inspect present air-con piping (to re-lay 3 days later on as present piping is obstructing the freshly hacked entrance)
Day 29 : Air-conditional (supply work & product to set up Mitsubishi 10k solitary Starmex Inverter split-type ac unit, redesign system 3 piping for existing a/c, 2 years guarantee)
Day 29 Evening : Arrival of commode vanity bought from Ezbuy (60cm as well as 70cm)
Day 31 : Plumbing set up commode vanity, mirror cupboard, container, bidet spray, immediate heating unit, various other commode devices. Examination water stress of the hot water heater. To transform typical restroom mixer later on. Painter fixing living space as well as bed rooms wall surface Nippon paint to snow white. Set up cleaning equipment pipeline as well as snowy faucet. ID sent out woodworking jobs dimension today, to inspect as well as validate format after that can begin produce.
Day 34 : Many lights jobs (transformed from square downlight to round downlight) are done other than those in cooking area as well as bedroom (hunch is awaiting woodworking functions – cooking area cupboard, master closet), frameless (we believed is black structure) set panel was set up. Opennet moving as well as information factor.
Day 36: Send out the food preparation hob & hood over, acquired a collection of Aerogaz food preparation Hood & Hob at much less than $500. Obtained a low-cost brand name as well as design, not exactly sure if we will certainly prepare often. Design: Hood AZ-9100 Black, Year 2021 New, Touch Panel, No switches, 900mm, coupled with Hob 790×500, black, toughened up glass
Day 38: Get In Touch With ID when can done as well as handover (A: another month to finish all as well as handover) Idea it will certainly be done quickly given that development fairly well. Presume the hold-up is because of Covid-19 circumstance so woodworking job is postponed. No selection however to wait… … …
Day 39 : Send out the black mixer as well as black pipe over, to change the existing one (silver colour) in the typical restroom. New electric job done: moved the power indicate the left (also near the hood), changed master space brand-new power factor cable television area, hid brand-new information factor circuitry. Action footwear shelf, cupboard as well as drape track size.
Day 42 : Send out added restroom devices over. Preparation not to go to that constant hereafter given that it require another month to obtain the restoration done… (ADD: DIDN’T KNOW THAT I WILL CERTAINLY MARVEL IN THE FOLLOWING GO TO). Asked ID to take apart the existing buzzer. Kitchen area cupboard interior PVC selected earlier runs out supply, re pick one… On-going paint jobs
Day 47 : Last seen 5 days back. Fairly shocking when I come today. Flooring security paper was gotten rid of, particles was gotten rid of, basic cleansing is finished……Seem like relocating currently!!! Scent primary door paint, need to be doing paint functions today…
Day 48 : Come with daytime today to inspect the floor tile grouting, a great deal obtained cleaned off after the cleansing. Planned to do noting however there are a lot of… might obtain the ID / service provider to look at their very own… plaster repair is provided for some small split at restroom box-up.
Day 49 : Send out the ceiling repaired fabric drying out devices over so they can aid to take apart the existing one as well as transform to a brand-new set
Day 53 : No additional development
Day 54 : No better advance, go as well as validate the inclined bedframe dimension, inspect the frozen glass sticker label dimension, drape track dimension, as well as additionally art paint dimension~
Day 58 : Send out the boom sanctuary T-catch door magnet there, to change. encounter the ID~ he stated a couple of even more weeks can obtain the woodworking functions done, producing currently. To repair paint, recheck grouting, get rid of existing steel door lock as well as additionally take apart the existing buzzer outlet.
Day 67 : didnt came right here for a long time as a result of awaiting woodworking construction, remarkably, those products are right here as well as 50% of the woodworking functions is finished.
Day 68 : Gas pipeline, check hot water heater with electrical power on, go IKEA, no ideal drape size, obtained a collection of white large drapes, foam cushion, mirror as well as a few other products invested overall SGD 200+
Day 70: Shipment of M1 Asus router, purchase television at Courts. Called ID to look at approximated conclusion day, required another month. Worried on conclusion within 2 weeks. Required to move-in.
Day 72 : Get gateway paint product
Day 74 : Woodworking functions is finished today. Very first time fulfill painter in your home
Day 75 : ID upgraded us on the development today, some remaining job. Came for a fast browse through.

No editing and enhancing, real lights in your home.

Resale Apartment

Please strike the subscribe switch as well as similar to this video clip. thanks quite for seeing