Singapore HDB Restoration Day 83 – Hooray !!! MOVE-IN DAY !!!新家入伙



Singapore 5-room resale HDB remodelling

(check reno day 34 summaries for day1-34 development)
Day 34 : The majority of lights jobs (altered from square downlight to round downlight) are done other than those in cooking area and also bedroom (assumption is waiting on woodworking functions – cooking area cupboard, master closet), frameless (we believed is black structure) set panel was set up. Opennet moving and also information factor.
Day 36: Send out the food preparation hob & hood over, got a collection of Aerogaz food preparation Hood & Hob at much less than $500. Obtained a low-cost brand name and also version, not exactly sure if we will certainly prepare often. Version: Hood AZ-9100 Black, Year 2021 New, Touch Panel, No switches, 900mm, coupled with Hob 790×500, black, solidified glass
Day 38: Talk To ID when can done and also handover (A: another month to finish all and also handover) Idea it will certainly be done quickly considering that development rather well. Presume the hold-up results from Covid-19 circumstance so woodworking job is postponed. No option however to wait… … …
Day 39 : Send out the black mixer and also black pipe over, to change the existing one (silver colour) in the typical washroom. New electric job done: moved the power indicate the left (as well near the hood), customized master area brand-new power factor cable television area, hid brand-new information factor electrical wiring. Procedure footwear shelf, cupboard and also drape track size.
Day 42 : Send out added washroom devices over. Preparation not to check out that regular hereafter considering that it require another month to obtain the remodelling done… (ADD: DIDN’T KNOW THAT I WILL CERTAINLY MARVEL IN THE FOLLOWING BROWSE THROUGH). Asked ID to take down the existing buzzer. Cooking area cupboard interior PVC picked earlier runs out supply, re pick one… On-going paint jobs
Day 47 : Last gone to 5 days earlier. Rather unusual when I come today. Flooring defense paper was eliminated, particles was gotten rid of, basic cleansing is finished……Seem like relocating currently!!! Scent primary door paint, need to be doing paint functions today…
Day 48 : Come with daytime today to examine the ceramic tile grouting, a great deal obtained cleaned off after the cleansing. Planned to do noting however there are a lot of… might obtain the ID / service provider to examine their very own… plaster retouch is provided for some small split at washroom box-up.
Day 49 : Send out the ceiling repaired fabric drying out devices over so they can assist to take down the existing one and also transform to a brand-new set
Day 53 : No more development
Day 54 : No even more advance, go and also validate the inclined bedframe dimension, examine the frozen glass sticker label dimension, drape track dimension, as well as additionally art paint dimension~
Day 58 : Send out the boom sanctuary T-catch door magnet there, to change. encounter the ID~ he claimed 1 or 2 even more weeks can obtain the woodworking functions done, producing currently. To retouch paint, recheck grouting, eliminate existing steel door lock as well as additionally take down the existing buzzer outlet.
Day 67 : didnt came below for a long time because of waiting on woodworking manufacture, remarkably, those products are below and also 50% of the woodworking functions is finished.
Day 68 : Gas pipeline, check hot water heater with electrical power on, go IKEA, no ideal drape size, obtained a collection of white large drapes, foam bed mattress, mirror and also a few other products invested overall SGD 200+
Day 70: Distribution of M1 Asus router, get television at Courts. Called ID to examine approximated conclusion day, required another month. Worried on conclusion within 2 weeks. Required to move-in.
Day 72 : Acquire gateway paint product
Day 74 : Woodworking functions is finished today. Very first time satisfy painter in your home
Day 75 : ID upgraded us on the development today, some remaining job. Came for a fast check out.
Day 76 : Distribution & installment of bedframe & bed mattress, cleaning device, Samsung fridge, Samsung Q60A TELEVISION, cooking area quartz top, couch and also table. Drape pole installment, footwear cupboard installment, accumulate EZ get parcels, set up stand follower, found fractured fridge shelf and also record to Samsung.
Day 77 5/9 : Gateway paint, examination cleaning device tidy bedsheet
Day 79 : Pipes Functions (Sensing unit Cooking area faucet, typical washroom bidet & rainshower), brand-new washing shelf set up (done first ART self-test today)
Day 80 : Exchange incorrect LED light strips acquired, drape distribution, pot distribution, ez-buy beverages distribution, Hob & Gas installment by CityGas, opennet activation, Samsung fridge fractured shelf substitute, get 火炭炉&charcoal, 撒盐,米,茶叶
Day 81 : Fill fridge with beverages, established computer system table, installment of LED light strips (cooking area and also television location), obtained soundbar from Samsung,
Day 82 : Digital Lock Installment, washing post distribution, residence moving, net activation, cooking area door installment
Day 83 : Relocate 新家入伙仪式 挂红彩 汤圆 柴米油盐酱醋茶 安床 米缸 碗筷

No editing and enhancing, real lights in your home.