Singapore HDB Restoration Day 49 (Day Time)



Day 49 of restoration
Restoration Day Forty-Nine
Singapore 5-room resale HDB restoration

Day 1 – 3 : Hack
Day 5 – 19 (2 weeks) : Tiling (Living area, bed rooms, kitchen area, shower room)
Day 20 : Bathroom Doors, Bathroom Add-on Marking
Day 23 : 1st Paint Day (Ceiling, living area, bed spaces) + Gas Pipeline Installment, Dismantled Gas Meter
Day 26 : Paint (incorrect colour??), room doors & maindoor setups, examine existing air-con piping (to re-lay 3 days later on as existing piping is obstructing the freshly hacked entrance)
Day 29 : Air-conditional (supply work & product to mount Mitsubishi 10k solitary Starmex Inverter split-type ac unit, renovate system 3 piping for existing a/c, 2 years service warranty)
Day 29 Evening : Arrival of bathroom vanity bought from Ezbuy (60cm as well as 70cm)
Day 31 : Plumbing professional mounted bathroom vanity, mirror closet, container, bidet spray, immediate heating unit, various other bathroom devices. Examination water stress of the hot water heater. To alter usual shower room mixer later on. Painter fixing living area as well as bed rooms wall surface Nippon paint to snow white. Mounted cleaning device pipeline as well as snowy faucet. ID sent out woodworking jobs dimension today, to examine as well as validate design after that can begin make.
Day 34 : A lot of illumination jobs (altered from square downlight to round downlight) are done other than those in kitchen area as well as bedroom (hunch is waiting on woodworking functions – kitchen area closet, master closet), frameless (we assumed is black structure) set panel was mounted. Opennet moving as well as information factor.
Day 36: Send out the food preparation hob & hood over, got a collection of Aerogaz food preparation Hood & Hob at much less than $500. Obtained an affordable brand name as well as design, not exactly sure if we will certainly prepare regularly. Design: Hood AZ-9100 Black, Year 2021 New, Touch Panel, No switches, 900mm, coupled with Hob 790×500, black, toughened up glass
Day 38: Consult ID when can done as well as handover (A: another month to finish all as well as handover) Idea it will certainly be done quickly given that development rather well. Think the hold-up is because of Covid-19 scenario so woodworking job is postponed. No option yet to wait… … …
Day 39 : Send out the black mixer as well as black pipe over, to change the existing one (silver colour) in the usual shower room. New electric job done: moved the power indicate the left (also near the hood), changed master area brand-new power factor cord area, hid brand-new information factor circuitry. Action footwear shelf, closet as well as drape track size.
Day 42 : Send out added shower room devices over. Preparation not to see that regular hereafter given that it require another month to obtain the restoration done… (ADD: DIDN’T KNOW THAT I WILL CERTAINLY MARVEL IN THE FOLLOWING BROWSE THROUGH). Asked ID to take down the existing buzzer. Kitchen area closet interior PVC selected earlier runs out supply, re pick one… On-going paint jobs
Day 47 : Last seen 5 days earlier. Fairly unexpected when I come today. Flooring security paper was eliminated, particles was removed, basic cleansing is finished……Seem like relocating currently!!! Odor major door paint, ought to be doing paint functions today…
Day 48 : Come with daytime today to examine the floor tile grouting, a great deal obtained cleaned off after the cleansing. Planned to do noting yet there are a lot of… might obtain the ID / specialist to look at their very own… plaster repair is provided for some small fracture at shower room box-up.
Day 49 : Send out the ceiling dealt with fabric drying out devices over so they can aid to take down the existing one as well as alter to a brand-new set

No modifying, real illumination in your house.